§ 24-150. Removal of materials or equipment upon completion of work.  


Latest version.
  • All materials or equipment placed in or upon a street, sidewalk or public way in accordance with a permit issued under this division shall be removed and the street, sidewalk or public way shall be restored within five days after completion of new construction work and within two days after completion of repair work. In either case, the restoration of the street, sidewalk or public way shall be to the satisfaction of the Director of Public Works, who shall be notified upon completion of the restoration work.

    (Code 1993, § 25-63; Code 2004, § 90-148)